73.
Commissioners Court - Regular Session
Meeting Date:
09/13/2022
Title:
T5023 CR 200 Reconstruction Change Order #1 (Various Items)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of $26,798.12 for Project T5023 CR 200 Reconstruction (MA Smith Contracting) P: 285 Funding Source: Road Bond.

Background

This Change Order adds items for small signs to the contract that were identified in the plans, but not accounted for in the bid tabs. It also adds items for stripe elimination that were not included in the plans, but necessary for the tie-ins at each end of the project.

This Change Order also adds an item for lowering an existing AT&T communications line that was encountered during the Culvert 1 installation near the west ROW line.  

Following is a summary of new items required for this Change Order.
 
ITEM DESCRIPTION QTY UNIT
464-0001 24” STORM HDPE N12 180 LF
644-6001 IN SM SN SUP&AM TY10BWG (1) SA(P) 11 EA
644-6060 IN SM SN SUP&AM TYWT (1) WS (P) 8 EA
677-6001 ELIM EXIST PM 4” 3400 LF
677-6003 ELIN EXIST PM 8” 97 LF
677-6005 ELIM EXIST PM 12” 231 LF
999-WC04 LOWERED FIBER OPTIC CABLE 1 EA
999-WC05 5% MARK-UP FOR SUB (STRIPING) 1 LS

This Change Order results in a net increase of $26,798.12 to the Contract amount, for an adjusted Contract total of $5,002,313.21. The original Contract amount was $4,975,515.09. As a result of this and all Change Orders to-date, $26,798.12 has been added the Contract, resulting in an 0.54% net increase in the Contract cost. No additional days will be added to or deducted from the Contract because of this Change Order. 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 09/08/2022 11:26 AM
Form Started By:
Julissa Romero
Started On:
09/08/2022 08:04 AM
Final Approval Date:
09/08/2022