22IFB57 CR 401 Reconstruction Change Order #7 (Interim Balancing)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 7 in the amount of $137,831.49 for Project 22IFB57 CR 401 Reconstruction (James Construction) P: 390 Funding Source: Road Bond.

Background

This Change Order adjusts quantities in the Contract due to unforeseen conditions that were identified in the field. This Change Order also adds items to the Contract to comply with additional UPRR requirements introduced after the bid opening, for work within UPRR ROW. See attached Change Order for details.

This Change Order results in a net increase of $137,831.49 to the Contract amount, for an adjusted Contract total of $14,041,894.83. The original Contract amount was $12,673,200.94. As a result of this and all Change Orders to-date, $1,368,693.89 has been added to the Contract, resulting in a 10.80% net increase in the Contract cost. No additional days will be added to the Contract as a result of this Change Order.
 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 01/25/2024 10:38 AM
Form Started By:
Julissa Romero
Started On:
01/24/2024 02:43 PM
Final Approval Date:
01/25/2024