32.
Commissioners Court - Regular Session
- Meeting Date:
- 11/19/2024
- Title:
- SJ&J Construction 24IFB6 CO1 Cross Culverts Replacements
- Submitted For:
- Robert Daigh
- Submitted By:
- Vicky Edwards, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on Change Order No 1 to contract number 24IFB6 for SJ&J Construction LLC in the amount of $4,632.50 for Cross Culvert Replacements FY 2024. Funding Source: 01.0200.0210.003599.
Background
This change order is a balancing change order. All work has been completed. The original contract amount was $554,554.07. With the addition of this Change Order in the amount of $4,632.50, the final contract amount will be $559,186.57.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 11/13/2024 03:24 PM |
- Form Started By:
- Vicky Edwards
- Started On:
- 11/12/2024 02:30 PM
- Final Approval Date:
- 11/13/2024