Skip to main content

AgendaQuick™

View Agenda Item

71.
Commissioners Court - Regular Session
Meeting Date:
02/25/2025
Title:
23IFB8 Corridor H - Sam Bass Road Change Order #6 (CORR)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 6 in the amount of $182,734.17 for Project 23IFB8 Corridor H Sam Bass Road (Cash Construction) P: 462 Funding Source: Road Bond.

Background

This Change Order adds new items requested by the City of Round Rock (CORR) for installing a thrust block on the backside of a tie-in to an existing line and for adding another 36-inch Gate Valve near FM 1431.
This Change Order also compensates the Contactor for work added to the Contract due to various existing Utility conflicts with the proposed City of Round Rock water line work. These changes are necessary to keep the project moving forward in a timely manner. The City of Round Rock has agreed to compensate the Contractor for this added work. Multiple items will be added by this Change Order. Please see attached Change Order.
This Change Order results in a net increase of $182,734.17 to the Contract amount, for an adjusted Contract total of $34,135,707.51. The original Contract amount was $36,145,959.00. As a result of this and all Change Orders to-date, $2,010,251.49.  Has been deducted from the Contract, resulting in a 5.56% net decrease in the overall Contract cost. No time will be added to the Contract for this Change Order.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Delia Colon 02/19/2025 01:54 PM
Form Started By:
Julissa Romero
Started On:
01/29/2025 09:12 AM
Final Approval Date:
02/19/2025