65.
Commissioners Court - Regular Session
- Meeting Date:
- 09/23/2025
- Title:
- FM 3349-US 79 Interchange Project - Advanced Funding Agreement – Amendment #1
- Submitted By:
- Ragan Riggs, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action on an Advanced Funding Agreement, Amendment No. 1 with TxDOT regarding the construction of the FM 3349-US 79 Interchange Project.
Background
This Amendment No. 1 to the Advanced Funding Agreement, signed on June 22, 2022, provides additional budget to the FM 3349-US 79 Interchange Project in the amount of $25,029,700.00 from $94,811,760.00 to $119,841,460.00. Project: P332 Funding Source: Road Bond
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Delia Colon | 09/16/2025 04:22 PM |
- Form Started By:
- Ragan Riggs
- Started On:
- 09/15/2025 01:57 PM
- Final Approval Date:
- 09/16/2025