27.
Commissioners Court - Regular Session
Meeting Date:
11/25/2025
Title:
25IFB64 Skyview Drive Bridge - Change Order #1
Submitted For:
Matt Williamson
Submitted By:
Jenifer Favreau, Infrastructure
Department:
Infrastructure
Division:
Road & Bridge
Agenda Category:
Consent

Information

Agenda Item

Discuss, consider and take appropriate action regarding Change Order #1 in the amount of $34,896.39 for Project 25IFB64 Skyview Drive Bridge with Patin Construction. Funding Source: P 708.

Background

This Change Order revises and replaces construction plan sheet B15 which contains a typographical error. The design engineer has corrected the error which results in requiring additional reinforcing steel. The error was discovered after the contractor mobilized equipment, personnel, materials and initiated work. This change order compensates the contractor for the additional costs incurred with the plan revision. This change order also adds reflectorized delineators to enhance visibility for motorists through the work zone. The original contract amount was $1,522,460.00. With this change order in the amount of $34,896.39, the amended contract amount will be $1,557,356.39. This change order increases the original contract amount by 2.29%.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Delia Colon 11/19/2025 08:37 AM
Form Started By:
Jenifer Favreau
Started On:
11/18/2025 02:37 PM
Final Approval Date:
11/19/2025