44.
Commissioners Court - Regular Session
- Meeting Date:
- 12/16/2025
- Title:
- CR 110 North – RPS – SWA#7 to WA#1
- Submitted By:
- Ragan Riggs, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider, and take appropriate action on Supplemental No. 7 to Work Authorization No. 1 to the CR 110 North contract executed March 19, 2024, between Williamson County and RPS Infrastructure, Inc. relating to the 2023 Road Bond Program.
Background
This Supplemental No. 7 to Work Authorization No. 1 extends the termination date to February 28, 2026. Project: P695 Fund Source: Road Bond Program
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Delia Colon | 12/09/2025 12:30 PM |
- Form Started By:
- Ragan Riggs
- Started On:
- 12/08/2025 04:20 PM
- Final Approval Date:
- 12/09/2025