- Jail North Generator Upgrade – Ramirez-Simon Engineering, LLC - Supplemental Agreement No 1
- Submitted For:
- Dale Butler
- Submitted By:
- Gretchen Glenn, Facilities Management
- Department:
- Facilities Management
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider, and take appropriate action on approving the Supplemental Agreement for Design and Engineering Services between Williamson County and Ramirez-Simon Engineering, LLC relating to the Jail North Generator Upgrade project.
Public Background
This Supplemental Agreement for Design and Engineering Services between Williamson County and Ramirez-Simon Engineering, LLC provides compensation for owner-requested services outside the original scope of work. The supplemental services include additional civil engineering work necessary to address Geological Assessment requirements associated with the Jail North Generator Upgrade project. The agreement increases the contract amount by $6,380.00 and extends the contract term through February 17, 2029. Funding will be provided from Account No. 01.0100.0509.004100.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Delia Colon | 07/09/2026 04:09 PM |
- Form Started By:
- Gretchen Glenn
- Started On:
- 07/09/2026 11:41 AM
- Final Approval Date:
- 07/09/2026