Subject
Adopt resolution requesting a time extension to the California Department of Water Resources Funding Agreement for the Huff's Corner Levee Raise & Channel Reconfiguration Project. (No general fund impact) (Echiburu/Sabatini)
Recommended Action
Adopt resolution requesting a time extension to the California Department of Water Resources Funding Agreement for the Huff's Corner Levee Raise & Channel Reconfiguration Project.
Strategic Plan Goal(s)
![]() |
Safe Communities |
![]() |
Sustainable Environment |
![]() |
Flourishing Agriculture |
Reason for Recommended Action/Background
On April 9, 2019, the Yolo County Board of Supervisors adopted Resolution No. 19-46 accepting funds from the California Department of Water Resources ("DWR") for a State-Federal Flood Control System Modification Program project titled: Huff's Corner Levee Raise & Channel Reconfiguration Project ("Project"). On August 7, 2019, the County and DWR executed Agreement No. 2019-FSRP-NA21-01 ("Project Agreement") for the Project. The Project involves raising the Huff's Corner Levee to its original design height and reconfiguration the Cache Creek channel to control erosional forces acting against the levee.
The California Legislature recently approved a provision to extend the deadline for the termination of Prop 1E funds. The Project is a recipient of these funds through DWR Agreement No. 4600013693 ("Agreement") (Attachment A). The Agreement terminates on December 31, 2022. Adoption of this resolution will formally request a 2-year extension to the Agreement. This extension is necessary for the County to fully utilize all the granted funds from DWR.
The California Legislature recently approved a provision to extend the deadline for the termination of Prop 1E funds. The Project is a recipient of these funds through DWR Agreement No. 4600013693 ("Agreement") (Attachment A). The Agreement terminates on December 31, 2022. Adoption of this resolution will formally request a 2-year extension to the Agreement. This extension is necessary for the County to fully utilize all the granted funds from DWR.
Collaborations (including Board advisory groups and external partner agencies)
The Office of County Counsel has approved the resolution as to form.
Fiscal Impact
No Fiscal Impact
Fiscal Impact (Expenditure)
- Total cost of recommended action:
- $
- Amount budgeted for expenditure:
- $
- Additional expenditure authority needed:
- $
- On-going commitment (annual cost):
- $
Source of Funds for this Expenditure
- General Fund
- $0
Further explanation as needed:
There is no fiscal impact associated with this action. A two-year extension to the DWR Agreement will not result in any additional project expenses not originally budgeted.
The total project amount is $2,845,000. The agreement between the County and the State establishes a cost share split of 85% State ($2,418,250) and 15% local ($426,750). The local cost share is funded by the Cache Creek Resources Management Plan.
The total project amount is $2,845,000. The agreement between the County and the State establishes a cost share split of 85% State ($2,418,250) and 15% local ($426,750). The local cost share is funded by the Cache Creek Resources Management Plan.