Consent-General Government # 17.
Board of Supervisors
General Services
- Meeting Date:
- 04/04/2023
- Brief Title
- Adopt Plans & Specifications for Agriculture Department Corp Yard
From:
Ryan Pistochini, Director, General Services Department
Staff Contact:
Mike Martinez, Projects Division Manager, General Services Department, x5015
Supervisorial District Impact:
Countywide
Subject
Adopt plans and specifications for the new Agriculture Department Corporation Yard, authorize the Director of General Services (or designee) to advertise for construction bids, and find that the project is exempt from the California Environmental Quality Act (CEQA). (No general fund impact) (Pistochini/Martinez)
Recommended Action
- Adopt plans and specifications for the Agriculture Department Corporation Yard, on file with the Clerk of the Board;
- Authorize the Director of General Services, or designee to advertise for construction bids; and
- Find the project is exempt from CEQA and authorize filing a Notice of Exemption (Att.A)
Strategic Plan Goal(s)
![]() |
Safe Communities |
![]() |
Sustainable Environment |
![]() |
Flourishing Agriculture |
![]() |
In Support of All Goals (Internal Departments Only) |
Reason for Recommended Action/Background
The Agriculture Department is in need of replacing two corporation yard buildings at 70 Cottonwood Street, Woodland as both buildings no longer meet the County's needs. The two buildings were constructed in 1954 and 1966 and have a combined square footage of 13,000. The Agriculture Department offices are located in a third building, Norton Hall, that was constructed in 1954.
The General Services Department conducted a review of county assets and determined that the most cost-effective option is to relocate the Agriculture Department in two phases to the county-owned property at 120 West Main Street, Woodland. Phase 1 is to construct a new Agriculture Department corporation yard building. Phase 2 is to relocate and reuse a 120 West Main Street, Suite D to house the Agriculture Department offices.
In Phase 1, the new construction of the corporation yard building will be a 6,020 square foot building. This building will house the Pesticide ID Lab which will house staff essential in identifying harmful pests to agriculture, a Trapping Supply Room used to bait traps for the trapping program, the Metrology Lab which is used to conduct precise testing (by statute) of water, electric and vapor meters that are used to charge tenants, house Weights & Measures equipment needed for field-testing, and Parking Bays for sensitive vehicles to protect them from vandalism. General Services engaged Comstock Johnson Architects to develop plans and specifications for the new building. A building permit was issued in December 2022. Public Contract Code §20150.12 requires this Board to approve the plans and specifications for this project. Upon your approval of the plans and specifications and the authorization by this Board today, the Procurement Division will advertise the project soliciting construction bids. After the completion of the competitive solicitation process, staff will return to this Board with a recommendation of award and execution of the contract, along with taking any formal budget action required through a budget resolution. The fiscal impact section of the staff report describes planned funding sources to completed the project and the anticipated date for construction start is summer 2023.
With today's adoption the plans and specifications (on file with the Clerk of the Board), the Director of General Services (or designee) can move the advertisement for construction bids. A CEQA notice of exemption is included as Attachment A for the Board's consideration and approval on the grounds described therein.
The General Services Department conducted a review of county assets and determined that the most cost-effective option is to relocate the Agriculture Department in two phases to the county-owned property at 120 West Main Street, Woodland. Phase 1 is to construct a new Agriculture Department corporation yard building. Phase 2 is to relocate and reuse a 120 West Main Street, Suite D to house the Agriculture Department offices.
In Phase 1, the new construction of the corporation yard building will be a 6,020 square foot building. This building will house the Pesticide ID Lab which will house staff essential in identifying harmful pests to agriculture, a Trapping Supply Room used to bait traps for the trapping program, the Metrology Lab which is used to conduct precise testing (by statute) of water, electric and vapor meters that are used to charge tenants, house Weights & Measures equipment needed for field-testing, and Parking Bays for sensitive vehicles to protect them from vandalism. General Services engaged Comstock Johnson Architects to develop plans and specifications for the new building. A building permit was issued in December 2022. Public Contract Code §20150.12 requires this Board to approve the plans and specifications for this project. Upon your approval of the plans and specifications and the authorization by this Board today, the Procurement Division will advertise the project soliciting construction bids. After the completion of the competitive solicitation process, staff will return to this Board with a recommendation of award and execution of the contract, along with taking any formal budget action required through a budget resolution. The fiscal impact section of the staff report describes planned funding sources to completed the project and the anticipated date for construction start is summer 2023.
With today's adoption the plans and specifications (on file with the Clerk of the Board), the Director of General Services (or designee) can move the advertisement for construction bids. A CEQA notice of exemption is included as Attachment A for the Board's consideration and approval on the grounds described therein.
Collaborations (including Board advisory groups and external partner agencies)
The General Services Department collaborated extensively with the Agriculture Department. Additional collaboration occurred with the Department of Financial Services, County Counsel and County Administrator's Office.
Competitive Bid Process/Vendor Performance
The competitive solicitation process will commence upon the Board's adoption of the plans and specifications and the authorization of the Director of General Services, or designee, to advertise the construction bids.
Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
- Total cost of recommended action:
- $ 3,900,000
- Amount budgeted for expenditure:
- $ 0
- Additional expenditure authority needed:
- $ 3,900,000
- One-time commitment:
- Yes
Source of Funds for this Expenditure
- Agriculture Capital Fund
- $1,432,000
- Development Impact Fees
- $1,858,000
- Accumulated Capital Outla
- $610,000
Further explanation as needed:
The engineer's estimate for the construction of the project is $3,900,000, which includes a 10% contingency. The Agriculture Department maintains an Agriculture Capital Fund and has accumulated $1,432,000, all of which is proposed to be designated to this project. The General Government category of Development Impact Fee has accumulated $4,756,000 of which $1,858,000 is proposed to be designated to this project. Recently $1,246,000 was dedicated to the Cannabis Modular project leaving an amount remaining of $1,650,000 for future projects that meet this category of the Development Impact Fee Study. Finally, the county plans to use $610,000 of Accumulated Capital Outlay funding to complete the budget of $3,900,000 toward the project.
A Budget Resolution is anticipated to come to the board with contract award.
A Budget Resolution is anticipated to come to the board with contract award.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Ryan Pistochini | Tonia Murphy | 03/27/2023 02:49 PM |
| Financial Services | Julie Dachtler | 03/27/2023 02:53 PM |
| County Counsel | Hope Welton | 03/28/2023 08:42 AM |
- Form Started By:
- Tonia Murphy
- Started On:
- 03/09/2023 09:43 AM
- Final Approval Date:
- 03/28/2023