Consent-Community Services # 7.
Board of Supervisors
Integrated Waste Management
- Meeting Date:
- 10/21/2025
- Brief Title
- Waste Management Unit 2 Drainage System Modifications
From:
Adam Fieseler, Director, Department of Community Services
Staff Contact:
Rachel Davis, Senior Civil Engineer, Department of Community Services, x8859
Supervisorial District Impact:
District 3
Subject
Approve and authorize the Manager of Procurement to execute Contract Change Order No. 1 to PO5856 with R.J. Gordon Construction, Inc. for $18,000 to complete construction of the Waste Management Unit 2 Drainage System Modification Project, which would increase the total contract amount to $150,000. (No general fund impact) (Davis/Fieseler)
Recommended Action
Approve and authorize the Manager of Procurement to execute Contract Change Order No. 1 to PO5856 with R.J. Gordon Construction, Inc. for $18,000 to complete construction of the Waste Management Unit 2 Drainage System Modification Project, which would increase the total contract amount to $150,000.
Strategic Plan Goal(s)
![]() |
Sustainable Environment |
Reason for Recommended Action/Background
In June 2025, the Yolo County Central Landfill (Landfill) was issued new 'Waste Discharge Requirements' (one of the Landfill's operating permits) from the Central Valley Regional Water Quality Control Board. This new permit required the Landfill to make a number of modifications to the site's stormwater drainage system, including portions of the system around Waste Managmenet Unit 2. R.J. Gordon Construction (Contractor) was awarded the contract (PO5856) through a competitive solicitation utilizing the procedures outlined in the California Uniform Public Construction Cost Accounting Act (CUPCCAA). During construction, it was identified that the project design placed the drainage ditch and culvert edge prohibitively close to the edge of a short section of the Landfill's main access road. This would, if constructed, represent a safety risk to Landfill customers. The Landfill engineering team worked with the Contractor to identify the most cost-effective design modification to solve the safety risk posed by the original culvert alignment and prepared a design revision.
The design revision includes extending the culvert further from the roadway into the drainage ditch along the north side of the Landfill and modification of the adjoining ditch that flows from south to north along the western edge of the Landfill. Landfill engineering staff has reviewed Change Order No. 1 to PO5856, including its scope and cost estimate, and recommends approval for the reasons set forth below.
The additional cost for the construction work described above exceeds the statutory contract change order limits for Public Contract Code section 20137. Changes exceeding the Public Contract Code section 20137 limit would ordinarily require competitive bidding. However, under Graydon v. Pasadena Redevelopment Agency (1980) 104 Cal.App.3d 631, competitive bidding is not required where the Board finds that such bidding would be unavailing and impractical and would not produce any public advantage. For the following reasons, competitive bidding for the additional drainage work in this case would not have produced any public advantage, and it is in the County's and the public's best interest to work with the existing Contractor on the project rather than competitively bid for the limited project changes.
- Each of the items of the contract change order work is functionally integrated with the overall Project.
- The Contractor is already mobilized and onsite doing the Project construction and able to complete the additional work at the same unit prices in its competitive bid.
- It wouldn't be practical to have a different contractor perform the change order work items because they are integrated with the overall infrastructure being installed, and trying to advertise and competitively bid the remaining items for the Project at this juncture would only further delay completion of the Project at additional expense.
Collaborations (including Board advisory groups and external partner agencies)
The Division of Integrated Waste Management worked with the Department of General Services on this change order.
Competitive Bid Process/Vendor Performance
The Waste Management Unit 2 Drainage System Modifications project was solicited through the procedures outlined in the California Uniform Public Construction Cost Accounting Act (CUPCCAA) using the approved CUPCCAA contractor list. Two bids were received:
- R.J. Gordon Construction — $132,000.00
- Quam General Engineering — $225,749.03
Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
- Total cost of recommended action:
- $ 18,000
- Amount budgeted for expenditure:
- $ 18,000
- Additional expenditure authority needed:
- $ 0
- One-time commitment:
- Yes
Source of Funds for this Expenditure
- Sanitation Enterprise Fun
- $18,000
Further explanation as needed:
The FY 25-26 Sanitation Enterprise Fund includes a total of $150,000 for this work. Approval of this change order will not require additional expenditure authority.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Marissa Juhler | 09/26/2025 08:32 AM | |
| Marissa Juhler | 09/26/2025 08:33 AM | |
| Stephanie Cormier | Marissa Juhler | 09/26/2025 08:33 AM |
| Stephanie Cormier | Destiny Software | 09/26/2025 02:44 PM |
| Berenice Espitia | Destiny Software | 09/26/2025 03:17 PM |
| Marissa Juhler | Marissa Juhler | 09/29/2025 01:22 PM |
| Marissa Juhler | Marissa Juhler | 09/29/2025 03:01 PM |
| Stephanie Cormier | Stephanie Cormier | 09/30/2025 10:42 AM |
| Adam Fieseler | Adam Fieseler | 10/08/2025 11:16 AM |
| Financial Services | KauXue Thao | 10/08/2025 01:04 PM |
| County Counsel | Hope Welton | 10/08/2025 02:06 PM |
| Berenice Espitia | Berenice Espitia | 10/10/2025 11:23 AM |
- Form Started By:
- Rachel Davis
- Started On:
- 09/25/2025 04:55 PM
- Final Approval Date:
- 10/10/2025
.png)