Consent-Community Services   # 7.
Board of Supervisors
Natural Resources
Meeting Date:
10/22/2024
Brief Title
Contract Change Order for Nordic Industries, Inc.
From:
Leslie Lindbo, Director, Department of Community Services
Staff Contact:
Elisa Sabatini, Manager of Natural Resources, Department of Community Services, x5773
Supervisorial District Impact:
Districts 3 & 5

Subject

Ratify Contract Change Order No. 001 to Agreement No. 24-208 with Nordic Industries, Inc. in the amount of $64,301.79, authorizing unanticipated and necessary extra work required by Caltrans associated with the installation and removal of a temporary shoulder closure along Interstate 5 for the Huff's Corner Levee Maintenance Project. (No general fund impact) (Lindbo/Sabatini)

Recommended Action

Ratify Contract Change Order No. 001 to Agreement No. 24-208 with Nordic Industries, Inc. in the amount of $64,301.79, authorizing unanticipated and necessary extra work required by Caltrans associated with the installation and removal of a temporary shoulder closure along Interstate 5 for the Huff's Corner Levee Maintenance Project.

Strategic Plan Goal(s)

Sustainable Environment
Flourishing Agriculture
County Mandated Service

Reason for Recommended Action/Background

Staff is recommending that the Board of Supervisors ratify a Contract Change Order ("CCO") to Agreement No. 24-208, a construction contract with Nordic Industries, Inc. (the "Contractor"), for the Huff's Corner Levee Maintenance Project (the "Project"). The Project is an element of the Huff's Corner Levee Raise & Channel Reconfiguration Phase II Project, which is funded by a Funding Agreement between the California Department of Water Resources and the County. 

The Project involves raising a 0.3-mile stretch of the County-maintained "Huff's Corner Levee" back to its original design profile. The levee is located along the right bank of Cache Creek, extending from County Road 18 to Interstate 5 ("I-5"). The Project encroaches on the existing Caltrans' Right-of-Way ("ROW") near I-5. The specific work to be completed within the ROW includes re-establishment and grading of the levee prism to the design criteria, as well as tying the levee embankment into the highway embankment. Lastly, a fence is to be installed at the edge of the ROW.  The County successfully obtained an Encroachment Permit for these project activities to occur within the Caltrans' ROW.

The Board of Supervisors approved the award for a construction contract to Nordic Industries, Inc. in the amount of $831,000 on July 23, 2024, and authorized the Director to approve change orders consistent with the applicable change order limits of the Public Contract Code, up to a cumulative total of 10% of the contract value.  During a pre-construction field meeting between the Contractor (Nordic) and Caltrans, it was noted by the Caltrans representative that the right shoulder of southbound I-5 would need to be closed when construction work was occurring within the Caltrans' ROW.  Because this requirement was not clearly stated in the Encroachment Permit the County obtained for the Project, the associated traffic control work was not included in the Bid Schedule when the construction contract was put to bid.  On September 16, 2024, the Contractor submitted a letter to County staff regarding a "change in conditions" that detailed their plan to address the need for the unanticipated traffic control work.  The letter also included a cost estimate for the work.  The contents of the letter were reviewed by County staff, as well as the Project Team, and the work plan and cost estimate were found to be appropriate. 

No construction activities are permitted to occur after October 31, 2024, without prior approval from the regulatory agencies.  As a result, the County and Contractor needed to work quickly to get the traffic control work scheduled, and the shoulder closure installed, to avoid serious delays in the Project.  If the traffic control work was not completed by the end of the week of September 16, the Project would have been delayed by 2-3 weeks due to the availability of the crew trained to perform the work.  As a result, staff was unable to bring the CCO to the Board of Supervisors for approval prior to the work commencing, and the CCO No. 001 was approved by the Director of Community Services (the "Director") on September 18, 2024 (Attachment A).  The work was completed on September 20, 2024.  A representative photo of the shoulder closure has been included as Attachment B. As of the drafting of this staff report, the Project is tracking to be completed on schedule and within the construction season period prescribed by the Project's permits.  Although the CCO No. 001 in the amount of $64,301.79 is within the cumulative 10% Project contingency ($83,100) approved by the Board on July 24, 2024, the amount of this CCO exceeds the Director's per change order authority per the Public Contract Code, and thus Board ratification is required for this particular change order.   

Collaborations (including Board advisory groups and external partner agencies)

Office of County Counsel

Competitive Bid Process/Vendor Performance

On May 22, 2024, an Invitation For Bids (reference no. GSDIFBKK2414) was released for construction services related to the Huff's Corner Levee Maintenance Project.  A total of 2 bids were submitted. Nordic Industries, Inc. was deemed to be the lowest responsive and responsible bidder. The resulting construction agreement (Agreement No. 24-208), in the amount of $831,100, was approved by the Board of Supervisors on July 23, 2024 (Minute Order No. 24-72; Item No. 9).

Fiscal Impact

No Fiscal Impact

Fiscal Impact (Expenditure)

Total cost of recommended action:
$    64,302
Amount budgeted for expenditure:
$    64,302
Additional expenditure authority needed:
$    0
One-time commitment:
Yes

Source of Funds for this Expenditure

DWR Funding
$57,872
Local Funding
$6,430

Further explanation as needed:

The Huff's Corner Levee Raise & Channel Reconfiguration Project Phase II is funded by a Project Partnership Agreement between the County and DWR (Yolo County Agreement No. 23-248; DWR Agreement No. 4600015709), which establishes a cost share split of 90% State and 10% County. The local cost share is funded by the Cache Creek Resources Management Plan fund. The estimated cost share of expenses associated with this amendment can be found above. All expenditures associated with the request can be adequately funded by appropriations included in the FY 24-25 Adopted Budget.

Attachments

Form Review

Inbox Reviewed By Date
Kimberly Hood Kimberly Hood 10/11/2024 12:35 PM
Stephanie Cormier Stephanie Cormier 10/14/2024 09:34 AM
Financial Services David Estrada 10/14/2024 12:44 PM
County Counsel Hope Welton 10/14/2024 01:38 PM
Berenice Espitia Berenice Espitia 10/14/2024 02:53 PM
Form Started By:
cliebler
Started On:
09/23/2024 10:47 AM
Final Approval Date:
10/14/2024