Consent-Community Services # 11.
Board of Supervisors
County Service Areas
- Meeting Date:
- 12/03/2024
- Brief Title
- Wild Wings Wood Duck Well Phase 2 Plans and Technical Specifications
From:
Dirk Brazil, Interim County Administrator
Staff Contact:
Yana Pavlova, County Service Areas Manager, County Administrator's Office, x8157
Supervisorial District Impact:
District 3
Subject
Adopt modified plans and specifications for the Wood Duck Well Phase 2 construction for the Wild Wings County Service Area; authorize the CSA Manager to sign the Notice to Bidders; and authorize the CSA Manager and the Procurement Division to advertise for competitive bids. (No general fund impact) (Brazil/Pavlova)
Recommended Action
- Adopt the updated plans and technical specifications for the Wood Duck Well Phase 2 construction;
- Authorize the CSA Manager to sign the Notice to Bidders; and
- Authorize the CSA Manager and the Procurement Division to advertise for competitive bids.
Strategic Plan Goal(s)
![]() |
Thriving Residents |
Reason for Recommended Action/Background
The Wild Wings County Service Area (CSA) operates two groundwater well stations, the Canvasback and Pintail wells. The Canvasback well is currently on standby status, meaning it cannot be used for potable water except in limited emergencies. The Wild Wings CSA therefore only has one potable water well, the Pintail well. In the past few years, the local groundwater levels in the Wild Wings CSA declined at an accelerated rate due to prolonged drought conditions, leading to concerns about the long-term viability of only one drinking water well.
In August 2021, County staff applied for grant funding for the construction of a new potable water supply well (the Wood Duck well), and an arsenic treatment system program at the community's existing Pintail well. The goal was to increase water supply reliability and create redundancy. In November 2021, the Department of Water Resources (DWR) awarded Small Community Drought Relief program grant funding to support the projects, in the amount of approximately $3.8 million. Design work for the projects began, and the Board of Supervisors adopted an Initial Study/Mitigated Negative Declaration and approved the projects on January 24, 2023. On July 11, 2023, the Board adopted the plans and specifications for the Wood Duck well construction and authorized the Community Services department to post bids for the project.
Bids for both the Wood Duck well project and the Pintail arsenic treatment system project opened on September 14, 2023. Unfortunately, bids came in significantly higher than expected, and significantly higher than DWR grant funding allowed. The lowest bid for the Wood Duck well construction was approximately $5.7 million, which exceeded both the remaining grant funding and the community water fund's ability to cover the expense. As a result, the arsenic project and the Wood Duck well project had to be bifurcated. Construction on the arsenic project began in late 2023 and is anticipated to conclude in Spring 2025. Work on the Wood Duck well was stalled while the CSA Manager considered how to move forward in light of high cost pressures.
In Summer 2024, the CSA Manager began exploring the option of phasing the Wood Duck well project with Luhdorff and Scalmanini Consulting Engineers (LSCE), the engineering firm behind the design of the well. The parties worked on a two-phase solution where Phase 1 would consist of installation of the well pump station and Phase 2 would include a raw water and/or drinking water transmission line. The Wood Duck well is anticipated to be fully operational as an irrigation source after the completion of Phase 1, but would not be fully integrated into the drinking water supply until Phase 2 is completed. The Phase 1 plans and technical specifications were adopted by the Board of Supervisors on November 5, 2024. The Phase 2 plans and technical specifications are included here as Attachment A and Attachment B, respectively.
Staff recommends approval of the Phase 2 plans and technical specifications, as doing so will allow the County Procurement Department to solicit bids for construction. The CSA Manager will continue to negotiate contingency funding with DWR, as well as continue to explore additional funding options to complete Phase 2 of the well project. If further modifications are necessary to complete the Wood Duck well project, staff will return to the Board of Supervisors with such information and potential award of a construction contract, depending on availability of DWR funding.
In August 2021, County staff applied for grant funding for the construction of a new potable water supply well (the Wood Duck well), and an arsenic treatment system program at the community's existing Pintail well. The goal was to increase water supply reliability and create redundancy. In November 2021, the Department of Water Resources (DWR) awarded Small Community Drought Relief program grant funding to support the projects, in the amount of approximately $3.8 million. Design work for the projects began, and the Board of Supervisors adopted an Initial Study/Mitigated Negative Declaration and approved the projects on January 24, 2023. On July 11, 2023, the Board adopted the plans and specifications for the Wood Duck well construction and authorized the Community Services department to post bids for the project.
Bids for both the Wood Duck well project and the Pintail arsenic treatment system project opened on September 14, 2023. Unfortunately, bids came in significantly higher than expected, and significantly higher than DWR grant funding allowed. The lowest bid for the Wood Duck well construction was approximately $5.7 million, which exceeded both the remaining grant funding and the community water fund's ability to cover the expense. As a result, the arsenic project and the Wood Duck well project had to be bifurcated. Construction on the arsenic project began in late 2023 and is anticipated to conclude in Spring 2025. Work on the Wood Duck well was stalled while the CSA Manager considered how to move forward in light of high cost pressures.
In Summer 2024, the CSA Manager began exploring the option of phasing the Wood Duck well project with Luhdorff and Scalmanini Consulting Engineers (LSCE), the engineering firm behind the design of the well. The parties worked on a two-phase solution where Phase 1 would consist of installation of the well pump station and Phase 2 would include a raw water and/or drinking water transmission line. The Wood Duck well is anticipated to be fully operational as an irrigation source after the completion of Phase 1, but would not be fully integrated into the drinking water supply until Phase 2 is completed. The Phase 1 plans and technical specifications were adopted by the Board of Supervisors on November 5, 2024. The Phase 2 plans and technical specifications are included here as Attachment A and Attachment B, respectively.
Staff recommends approval of the Phase 2 plans and technical specifications, as doing so will allow the County Procurement Department to solicit bids for construction. The CSA Manager will continue to negotiate contingency funding with DWR, as well as continue to explore additional funding options to complete Phase 2 of the well project. If further modifications are necessary to complete the Wood Duck well project, staff will return to the Board of Supervisors with such information and potential award of a construction contract, depending on availability of DWR funding.
Collaborations (including Board advisory groups and external partner agencies)
Luhdorff and Scalmanini Consulting Engineers completed the updated plans and technical specifications to phase the Wood Duck well project. The Wild Wings County Service Area Advisory Committee has received updates about the status of the Wood Duck well project in their regularly scheduled meetings. The Department of Water Resources of the State of California is aware of the phasing of the project. The County Procurement Department is drafting the bidding documents and would solicit construction bids.
Competitive Bid Process/Vendor Performance
Phase 2 of the Wood Duck well project would undergo a competitive bid process, which will be completed in accordance with state law.
Fiscal Impact
Potential fiscal impact (see notes in explanation section below)
Fiscal Impact (Expenditure)
- Total cost of recommended action:
- $
- Amount budgeted for expenditure:
- $
- Additional expenditure authority needed:
- $
- One-time commitment:
- Yes
Source of Funds for this Expenditure
- General Fund
- $0
Further explanation as needed:
There would be no impact to the general fund as a result of this action. After assessing whether awarding Phase 2 of the Wood Duck well is feasible given budgetary constraints, and depending on bid results, the costs would be covered through a combination of the Wild Wings Water Fund and DWR grant funds (if any are available). If sufficient funding is available, staff will return to the Board to consider awarding of the construction contract for Phase 2.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Kimberly Hood | Kimberly Hood | 11/20/2024 05:20 PM |
| Mark Bryan | Mark Bryan | 11/21/2024 10:02 AM |
| Financial Services | mrobertson | 11/22/2024 08:02 AM |
| County Counsel | Hope Welton | 11/22/2024 11:33 AM |
| Cindy Perez | Cindy Perez | 11/22/2024 11:41 AM |
- Form Started By:
- ypavlova
- Started On:
- 11/05/2024 01:50 PM
- Final Approval Date:
- 11/22/2024
.png)