Consent-Community Services # 6.
Board of Supervisors
County Service Areas
- Meeting Date:
- 07/07/2026
- Brief Title
- Amendment to Agreement with Ponticello Consulting Engineers, Inc.
From:
Michael Webb, County Administrator, County Administrator's Office
Staff Contact:
Yen Nguyen, County Service Area Manager, County Administrator's Office, x8157
Supervisorial District Impact:
District 2
Subject
Approve thirteenth amendment to Agreement No. 7676-2017 with Ponticello Consulting Engineers, Inc. for engineering consulting services related to the North Davis Meadows County Service Area Water Consolidation Project to increase the maximum compensation by $10,000 to $295,000. (No general fund impact) (Webb/Nguyen)
Recommended Action
Approve thirteenth amendment to Agreement No. 7676-2017 with Ponticello Consulting Engineers, Inc. for engineering consulting services related to the North Davis Meadows County Service Area Water Consolidation Project to increase the maximum compensation by $10,000 to $295,000.
Strategic Plan Goal(s)
![]() |
Thriving Residents |
![]() |
Collaborative Community |
Reason for Recommended Action/Background
Yolo County has been working to address significant water quality issues in the North Davis Meadows (NDM) County Service Area (CSA) for over a decade. In 2017, the NDM community expressed an interest in connecting to the City of Davis for water service to address water quality concerns (the "Water Consolidation Project"). The County entered into a contract with Ponticello Consulting Engineers, Inc. ("Ponticello") in January 2017 for project management services for the extension of potable water from the City of Davis to the North Davis Meadows community. Financing for this project began in 2018, and additional engineering was completed at that time. After a litigation delay that was resolved in favor of the County, the Water Consolidation Project resumed.
A construction bid was posted in the spring of 2024. The County received a total of five bids, with Soracco, Inc. providing the lowest responsive and responsible bid at approximately $3.6 million. The Board of Supervisors approved the award of the construction contract to Soracco, Inc. on August 27, 2024, and the County issued the Notice to Proceed on September 30, 2024. Construction began in October 2024. Ponticello has been instrumental in providing project management services for the Water Consolidation Project. As part of its services, Ponticello has assisted with ensuring the Water Consolidation Project stays within budget, coordinated with the State Water Resources Control Board for grant administration, monitored construction activities, and coordinated with the City of Davis, permitting agencies, and/or other entities as needed. Construction was delayed due to water pressure concerns. In March 2026, the City of Davis installed an altitude valve to increase the water system pressure. Tie-in to the City of Davis water system is expected to occur on Wednesday, July 8th, 2026.
Under the proposed Thirteenth Amendment (Attachment A), the Ponticello contract maximum compensation will increase by $10,000 from $285,000 to $295,000. Staff recommend the Board approve the Thirteenth Agreement to continue receiving project management services through the completion of the Water Consolidation Project, which will include grant close out activities. If further amendments are needed, County staff will return to the Board of Supervisors for direction.
Collaborations (including Board advisory groups and external partner agencies)
County Counsel approved as to form
General Services Department, Procurement Division
General Services Department, Procurement Division
Competitive Bid Process/Vendor Performance
The Department confirms Ponticello has performed satisfactorily on the current agreement.
Fiscal Impact
Fiscal impact (see budgetary detail below)
Fiscal Impact (Expenditure)
- Total cost of recommended action:
- $ 295,000
- Amount budgeted for expenditure:
- $ 295,000
- Additional expenditure authority needed:
- $ 0
- One-time commitment:
- Yes
Source of Funds for this Expenditure
- North Davis Meadows CSA
- $10,000
Further explanation as needed:
There is no impact to the general fund as a result of this action. The North Davis Meadows CSA Water Fund would cover the costs anticipated with this action. Some of the costs would likely be grant-eligible, and County staff plan to seek reimbursement from the State Water Resources Control Board for those costs.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Yen Nguyen (Originator) | Yen Nguyen | 06/26/2026 04:16 PM |
| Mark Bryan | Mark Bryan | 06/26/2026 04:30 PM |
| Michael Webb | Michael Webb | 06/29/2026 10:22 AM |
| Financial Services | Dylan Rader | 06/29/2026 12:11 PM |
| County Counsel | Hope Welton | 06/30/2026 11:16 AM |
| Cindy Perez | Paula Hugi | 06/30/2026 01:42 PM |
| Berenice Espitia | Berenice Espitia | 07/01/2026 11:35 AM |
- Form Started By:
- Yen Nguyen
- Started On:
- 06/11/2026 02:37 PM
- Final Approval Date:
- 07/01/2026
.png)
.png)