Brief Title
Agriculture Department Corporation Yard Construction Contract
From:
Ryan Pistochini, Director of General Services, General Services Department
Staff Contact:
Carlos del Rosario, Senior Project Coordinator, General Services Department, x4834
Supervisorial District Impact:
District 5

Subject

Adopt budget resolution increasing the Agriculture Department Corporation Yard Project Budget by $450,000 for a new Project Budget of $4,959,674 to cover additional project costs inclusive of remaining construction contract change orders, public art, furniture, specialized water testing bench, and other related project costs; authorize the Director of General Services to approve Contract Change Order to Yolo County Agreement No. 5616 with Creekside Commercial Builders Inc., in the amount of $13,645.93 along with a one month extension to complete the Yolo County Ag Shops Building Project located at 139 W Court Street in Woodland, resulting in a revised total contract price of $4,262,770.41 and authorize the Director of General Services to approve other change orders within the Project Budget; and approve the addition of a water testing table as a Fixed Asset to the 2026-27 Authorized Equipment List. (No general fund impact)  (4/5 vote required) (Pistochini/del Rosario)

Recommended Action

  1. Adopt a Budget Resolution (Att. A)  increasing the FY 2025-2026 appropriation for the Agriculture Department Corporation Yard Project Budget (Facilities Capital Project) by $450,000 for a revised Project Budget of $4,959,674 to cover remaining change orders to the construction contract (Agreement No. 5616), Public Art, IT equipment, furniture, building monitoring and moving of highly specialized equipment to the new location, including a water testing bench estimated to be around $200,000; 
     
  2. Authorize the Director of General Services to approve Contract Change Order to Yolo County Agreement No. 5616 with Creekside Commercial Builders Inc. in the amount of $13,645.93 (Att. B), increasing the total contract price to $4,262,770.41 with a one-month extension to November 30, 2026, to complete the Yolo County Agriculture Department Corporation Yard located at 139 W Court Street in Woodland, and further authorize the Director of General Services to approve other change orders within the Project Budget; and
     
  3. Approve the addition of a water testing table as a Fixed Asset to the 2026-27 Authorized Equipment List (Att. C.)

Strategic Plan Goal(s)

Reason for Recommended Action/Background

The County allocated a total project budget of $4,509,674 that was approved by the Board on January 14, 2025. With the Ag Shops Building Project nearing completion, the adopted project budget contingency allocated is depleting due to change orders related to various structural design changes, the conversion of the project to be all-electric, additional code compliance work, and smaller ancillary changes.  Approving the increase of the adopted budget resolution by $450,000 to cover the amendment to contract 5616, Public Art, IT equipment, furniture, building monitoring and moving of highly specialized equipment to the new location to complete the Yolo County AG Shops Building.  Staff are requesting a revised project budget of $4,959,674.

The County entered into a contract with Creekside Commercial Builders Inc. to complete the AG Shops Building located at 139 W Court Street in Woodland. Contract 5616 was approved by the Board of Supervisors on January 14, 2025 (Yolo County Agreement No. 25-07), for a total amount of $3,898,734, with authority for the Director of General Services to approve change orders and other contracts necessary to complete the contract up to a cumulative total of $389,873 (subject to individual change order limits in the Public Contract Code). Subsequent change orders issued were due to owner changes, code compliance, unforeseen conditions, and resolution of design conflicts. The total contract amount increased to $4,262,770.41. To finalize the project, and authorize a final set of proposed change orders, staff are requesting to approve an additional change order to Contract 5616 with Creekside Commercial Builders Inc. in the amount of $13,645.93, resulting in an increased total contract price of $4,262,770.41.  Staff are currently reviewing an additional owner requested change order to add additional electrical support equipment to support the Agriculture Department's request for a new water table.  This contract increase request and potential change order are reflected in the project budget increase request of $450,000.  Board authorization for these additional change orders is requested since the original change order cap and Project Budget must be increased above the amounts approved by the Board on January 14, 2025.

One major cost component of the project budget increase is to purchase a new water testing bench.  The Agriculture Department's current water testing bench is over 30 years old and was set up by staff by cobbling together parts from various sources. This water testing bench is a specialized piece of equipment necessary for the Agriculture Department to perform its weights and measures function.  Currently, the Agriculture Department is not able to test more than a handful of meters at a time due to the fact that the current bench is not able to meet the flow rate and pressure requirements set by the National Council on Weight & Measure (NCWM). The new bench will let the Agriculture Department test more meters per cycle and meets NCWM requirements.  The new bench will also need to be certified by the National Institute of Standards and Technology (NIST). The new bench also has automated features and software that will also help us work faster and ease record-keeping requirements, increasing our efficiency. 

Because the additional cost for the construction work described above may exceed the statutory contract change order limits for Public Contract Code section 20137, further change orders would ordinarily require competitive bidding. However, under Graydon v. Pasadena Redevelopment Agency (1980) 104.Cal.App.3d 631, competitive bidding is not required where such bidding would be unavailing and impractical and would not produce any public advantage.  For the following reasons, competitive bidding for the extra work in this case would not have produced any public advantage, and it is in both the best interest of the County and the public to work with the existing contractor on the Project rather than competitively bidding these Project changes because: 
  • Each of the items of the contract change order work is functionally integrated with the overall Project.
  • Creekside Commercial Builders is already mobilized and onsite doing the Project construction and able to complete the additional work by November 30, 2026, consistent with the pricing in its competitive bid.
  • It wouldn’t be practical to have a different contractor perform the change order work items because they are integrated with the overall infrastructure being installed and trying to advertise and competitively bid the remaining items for the Project at this juncture would only further delay completion of the Project at additional expense.
 
Project Expenditures $4,509,674
Construction Contract Change Order $13,646
Additional Project Expenses (pending future electrical support equipment change order moving expenses, furniture & equipment, IT hardware needs, Public Art Requirement) $226,304
Water Testing Bench $200,000
Project Management Fees $10,050
Total Project Expenditures $4,959,674

Collaborations (including Board advisory groups and external partner agencies)

The Department collaborated with the County Administrator's Office, Agriculture Department, and Department of Financial Services.

Competitive Bid Process/Vendor Performance

The General Services Department collaborated with the Agriculture Department to define the water testing bench requirements.

Fiscal Impact

Fiscal impact (see budgetary detail below)

Fiscal Impact (Expenditure)

Total cost of recommended action:
$    4,959,674
Amount budgeted for expenditure:
$   2,559,682
Additional expenditure authority needed:
$    450,000
One-time commitment:
Yes

Source of Funds for this Expenditure

CIP Bonds
$450,000

Further explanation as needed:

In working with the Department of Financial Services, the 2017 Capital Improvement Project Bonds is identified as the ideal funding source for this project budget amendment.  A portion of the project is already funded in part by the Bonds.  The total project budget, if the staff request is approved, is $4,959,674.  This project spans multiple fiscal years, and the remaining amount to be spent this fiscal year is originally 2,559,682 and is proposed to be increased to 3,009,682.

Attachments

Form Review

Inbox Reviewed By Date
Ryan Pistochini (Originator) Tonia Murphy 08/12/2026 04:42 PM
Ryan Pistochini (Originator) Ryan Pistochini 09/02/2026 10:17 PM
Financial Services Dylan Rader 09/03/2026 11:37 AM
County Counsel Kimberly Hood 09/03/2026 05:11 PM
Ryan Pistochini (Originator) Ryan Pistochini 09/17/2026 11:58 AM
County Counsel Kimberly Hood 09/17/2026 02:35 PM
Laura Galindo Laura Galindo 09/17/2026 02:44 PM
Form Started By:
Ryan Pistochini
Started On:
07/01/2026 09:29 AM
Final Approval Date:
09/17/2026