Consent-Community Services   # 6.
Board of Supervisors
Public Works
Meeting Date:
09/08/2026
Brief Title
Approve Agreement with Wood Rodgers
From:
Adam Fieseler, Director, Department of Community Services
Staff Contact:
Todd N. Riddiough, Director of Public Works, Department of Community Services, x8039
Supervisorial District Impact:
District 5

Subject

Approve agreement with Wood Rodgers, Inc. to provide engineering services to analyze current drainage conditions and assess the impact of adding sidewalks on select streets on the eastern side of the Town of Esparto for fiscal years 2026-27 through 2028-29, in a total amount not to exceed $255,441.74; and delegate authority to the Director of Public Works or the Director’s designee to sign the agreement and additional forms, documents, and/or amendments as necessary relating to this agreement, provided there is no increase to the total maximum compensation. (No general fund impact) (Fieseler/ Riddiough)

Recommended Action

  1. Approve agreement with Wood Rodgers, Inc. to provide engineering services to analyze current drainage conditions and assess the impact of adding sidewalks on select streets on the eastern side of the Town of Esparto for fiscal years 2026-27 through 2028-29, in a total amount not to exceed $255,441.74; and
     
  2. Delegate authority to the Director of Public Works or the Director’s designee to sign the agreement with Wood Rodgers, Inc. and to negotiate, sign and execute any additional forms, documents and/or amendments as necessary relating to this agreement, provided such amendments do not increase the maximum compensation of $255,441.74.

Strategic Plan Goal(s)

Thriving Residents

Reason for Recommended Action/Background

Approval of the agreement will allow the consultant, Wood Rodgers, to begin the work and to provide engineering services to analyze current drainage conditions and assess the impact of adding sidewalks on selected streets on the eastern side of Esparto.

BACKGROUND

Yolo County Department of Community Services, Public Works Division, applied for a Sacramento Area Council of Governments (SACOG) Community Design Funding Program Grant to hire a consultant to provide engineering services to analyze current drainage conditions and assess the impact of adding sidewalks on selected streets on the eastern side of Esparto to improve pedestrian access and safety.  The County received a $300,000 federal grant which requires an 11.47-percent local fund match. Public Works will provide the $34,410 local match through the Road Fund.

A Request for Proposals (RFP) was advertised on Beacon Bid in early 2026 and one proposal was received.  The RFP selection committee formed with representatives from the Public Works Division reviewed the proposal. The panel scored the technical merits of the proposal in a variety of categories, including qualifications of staff, customer references and experience with similar work. Wood Rodgers, Inc. was determined to be the most qualified bidder.  Staff negotiated the agreement in accordance with the process required for consultant contracts.

Upon completion of the drainage and feasibility study, Yolo County hopes to be poised to proactively address drainage issues and possible installation of sidewalks in select locations to improve pedestrian safety in this area of Esparto.

After negotiations and refining the scope of work, the consultant has agreed to a maximum compensation of $255,441.74 to complete the project. Any remaining matching fund amounts will help to cover a portion of staff efforts for the project.

Staff recommends the Board approve the contract with Wood Rodgers, Inc. included as Attachment A.

Collaborations (including Board advisory groups and external partner agencies)

County Counsel approved the agreement as to form.

Competitive Bid Process/Vendor Performance

Request for Proposals (RFP) Service Requested:  East Esparto Sidewalk Improvement Feasibility Study and Design Project, in Yolo County, California

A selection committee of staff engineers reviewed the proposal. Based on the requirements in the RFP, Wood Rogers was identified as the firm with the best qualifications and proposal. Staff negotiated a contract with Wood Rogers in accordance with the process required for consultant contracts.

Evaluation Criteria Included in RFP
  • Qualifications of Staff Experience with Similar Work (15 points)
  • Proposer's Understanding of the Project (35 points)
  • Customer References (10 points)
  • Financial Responsibility (10 points)
  • Quality and Completeness of Submitted Proposal (30 points)

Fiscal Impact

Fiscal impact (see budgetary detail below)

Fiscal Impact (Expenditure)

Total cost of recommended action:
$    255,442
Amount budgeted for expenditure:
$    334,410
Additional expenditure authority needed:
$    0
One-time commitment:
Yes

Source of Funds for this Expenditure

SACOG Grant
$300,000
Road Fund
$34,410

Further explanation as needed:

The FY 2026/2027 Road Fund budget includes this year's contract costs and the required local match. Future costs and matching funds will be budgeted in the Road Fund for the corresponding fiscal year. The SACOG Community Design Funding Program Grant totals $300,000. The county's share is capped at $34,410, the required 11.47 percent local match. The contract amount of $255,441.74 does not use the full $300,000 budgeted. The remaining will cover support staff time spent managing the project for a total cost up to $78,968.

Attachments

Form Review

Inbox Reviewed By Date
Todd Riddiough Todd Riddiough 08/26/2026 01:38 PM
Stephanie Silva Stephanie Silva 08/26/2026 01:44 PM
Kimberly Hood Kimberly Hood 08/31/2026 04:02 PM
Adam Fieseler Julie Dachtler 08/31/2026 04:03 PM
Todd Riddiough Todd Riddiough 09/01/2026 09:42 AM
Stephanie Silva Stephanie Silva 09/01/2026 10:01 AM
Kimberly Hood Kimberly Hood 09/02/2026 09:50 AM
Adam Fieseler Adam Fieseler 09/02/2026 02:35 PM
Financial Services Dylan Rader 09/03/2026 09:54 AM
County Counsel Julie Dachtler 09/03/2026 10:59 AM
Berenice Espitia Berenice Espitia 09/03/2026 12:43 PM
Form Started By:
Patricia Valenzuela
Started On:
07/13/2026 02:11 PM
Final Approval Date:
09/03/2026